Manitowoc Published 06-24-16, Control # 241-01 4-29
2250 OPERATOR MANUAL SETUP AND INSTALLATION
Install Assembly Block
NOTE: The circled numbers in Figure 4-16 correspond to
the numbers of the following steps.
Letters “A” and “B” indicate the sheave locations. Determine
the sheave configuration of your crane at the two locations
using the illustrations in Figure 4-16
. Then follow the reeving
pattern for those configurations.
1. Reeve the load line from the top of rear, right rear, or left
rear drum over the proper guide sheave A and proper
guide sheave B (see View A or B).
2. Reeve the load line through the assembly block.
3. Anchor the load line to the appropriate dead-end lug
(see View C or D). Use the dead-end socket and wedge
for a 29 mm (1-1/8 in) load line.
Raise Gantry
See Gantry Raising and Lowering (with Boom Butt Handling
Cylinder) on page 4-50 for more information.
NOTE: Fully retract the boom butt cylinder after the gantry
is fully raised.