Maintenance work on the carrier
7.15 Central lubrication system
7 - 104 3 302 577 en Maintenance manual
GMK7450
16.08.2018
Topping up
Fill the grease container as follows:
• Switch on the ignition.
• Remove the cap (3).
• Attach the filling pump to connection (1) or (2).
• Press the button (4) once for approx.
2 seconds.
Intermediate lubrication will be triggered.
• Fill the grease container up to the Max.
marking.
• Remove the filling pump, wipe away any
excess grease and close the holes.
S
Risk of damage to the central lubrication system!
Cleanliness is of the utmost importance when handling grease and filling
pumps.
Do not remove the caps from the opening and filling pump until immedi-
ately before refilling the grease. This prevents dirt particles from getting
into the gre
ase and damaging the central lubrication system.
1 Filling pump tool set:
You must install the connector from the
toolbox
.
2 Filling pumps for lubrication nipples

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Manitowoc GROVE GMK7450 and is the answer not in the manual?

Manitowoc GROVE GMK7450 Specifications

General IconGeneral
BrandManitowoc
ModelGROVE GMK7450
CategoryConstruction Equipment
LanguageEnglish

Related product manuals