Longer out of service periods
16.08.2018
Maintenance manual 3 302 577 en 9 - 1
GMK7450
9 Longer out of service periods
Carry out the following jobs if the truck crane is going to be out of service
for a long period (months).
Putting the truck
crane out o
f
service
• Clean the truck crane thoroughly on the inside and outside.
• Remove any rust and touch up the paintwork.
• Parts that are not painted must be lubricated with an acid-free grease or oil.
If more than half of the oil change interval has passed:
• Change the oil according to the maintenance plans M 3 to M 12.
• Seal all the air filters.
• Increase the tyre pressure by 10 % and mark the tyre positioning, or
support the truck crane and leave it standing on the outriggers.
• Observe the specifications on preservation in the Engine manufacturer’s
documentation
.
Checks
• Check the levels in the fuel tanks. Always keep the tanks filled.
• Check the batteries every week and recharge them if necessary.
• Check the tyre pressure every week and correct it if necessary.
• Perform a full functional test on the truck crane every two weeks.
(Open all air filters beforehand!)
• Run the hydraulic systems up to a fluid temperature of approx. 50 °C
(122 °F) and then check all functions of the carrier and superstructure
hydraulic systems.
s

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Manitowoc GROVE GMK7450 and is the answer not in the manual?

Manitowoc GROVE GMK7450 Specifications

General IconGeneral
BrandManitowoc
ModelGROVE GMK7450
CategoryConstruction Equipment
LanguageEnglish

Related product manuals