2 - 24 Chapter 2
Chapter 2 - Blade Installation and Startup
2.4.1.3 CCPU Installation (Figure 2-5 - Figure 2-6)
1. Install the battery on the CCPU. The polarity “+” symbol must be on top.
2. Install the Voice Mail, Memory, and/or VoIP daughter boards if required.
3. After being certain that the power supply is shut off, slide the CCPU into the CCPU slot in the
Controlling chassis.
● Note that the blades must be inserted into the chassis with the top of the blade up,
otherwise the connection to the backplane will not be made.
Figure 2-5: BATTERY INSTALLATION
Figure 2-6: INSTALLING BLADES
• The power to the chassis must be off when installing or removing
this blade.
• Do not remove/insert the optional CCPU daughter boards (VMDB,
MEMDB, VOIPDB) or voice mail flash card while the system power is on.
Battery
Battery Socket