4.2 Preparatory planning
4.2.1 Documentation
Configuration guidelines for the PCS 7 application
Approved specifications are a prerequisite for configuring a PCS 7 plant in the GMP
environment. Projects of this type generally follow the GAMP5 approach. The objectives in the
GAMP5 documents include: "Guide aims to achieve process control systems that are fit for
intended use and compliant with applicable regulations; providing recommended good practice
based on a life cycle approach for the development, maintenance, and management of process
control system.".
Adherence to the guidelines has a positive influence on the following aspects:
Compliance with legal regulations
Quality of the products
Production efficiency
Cost savings
Even in projects where there are less legal regulations to be complied with and not as many
high requirements related to quality and efficiency, a similar approach (e.g. the so-called GAMP
light) must be applied whereby only terms and phases from GAMP5 are used.
Preparation and administration
4.2 Preparatory planning
Compendium Part A - Configuration Guidelines (V8.2)