Returning the Server to Operation 151
● Power on the server by performing one of the following:
■ Press the Power button on the server front panel.
■ Log in to the Oracle ILOM web interface, click Host Management > Power
Control and select Power On from the Select Action list.
■ Log in to the Oracle ILOM command-line interface (CLI), and type the
following command at the Oracle ILOM CLI prompt.
When the server is powered on and the power-on self-test (POST) code checkpoint
tests have completed, the green Power/OK status indicator on the front panel
lights and remains lit.
Related Information
■ “Powering Down the Server” on page 33
■ “Reconnect Data Cables and Power Cords” on page 149
-> start /System