Cleaning / Disinfection
Cleaning and disinfection schedule
30 11/2020 243343V03_EN
3.8 Cleaning and disinfection schedule
The following information applies for single-shift operation.
Pre-cleaning (start at the end of production)
Work steps Cleaning agents Process Equipment Notes
Superficial clean-
ing
(removal of product
residues)
manual, mechanical Plastic spatula,
plastic scraper
Check the slits in
the grid.
Dismantling of
small parts
Pre-rinse thor-
oughly
Drinking water Low pressure below
30 bar
Temperature 50 °C
Low-pressure
device,
water hose
From top to bottom,
do not forget small
parts.
Check for visual
cleanliness
visual
Cleaning (alkaline or acid)
Work steps Cleaning agents Process Equipment Notes
Cleaning small
parts and grid
Ecolab:
1-2 %
P3 sterile
Clean manually in
basin with brush,
low-pressure less
than 30 bar
Reaction time: 15 to
30 min.
Temperature 40 °C
Low-pressure foam-
ing device,
hand spray device,
brush, basin
Spray small parts
from bottom to top
Alkali cleaning
(daily)
Ecolab:
2-5 %
P3 topax 19 or
P3 topax 66
foam,
low-pressure below
30 bar
Reaction time: 10 to
15 min.
Low-pressure foam-
ing device
Foam the machine
from bottom to top.
Acid cleaning
(If required,
approx. once per
week instead of
alkaline cleaning.
To remove calcium
residues)
Ecolab:
2-5 %
P3 topax 56
foam,
low-pressure below
30 bar
Reaction time:
15 min.
Low-pressure foam-
ing device
Foam the machine
from bottom to top.
Rinsing Drinking water Low pressure below
30 bar
Temperature up to
50 °C
Low-pressure
device,
water hose
Rinse entire
machine from top to
bottom, rinse small
parts on grating or
table.
Check for visual
cleanness
visual Particularly check
areas that that
come into contact
with the product and
adjacent areas.