EasyManua.ls Logo

Vertiv Liebert STS2 - Figure 25 Electrical Field Connections, 250 A Liebert STS2;PDU Input with CB3 & CB3 A

Vertiv Liebert STS2
160 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Vertiv | Liebert® STS2/PDU
User Manual | Rev. 6 | 10/2017 35
Figure 25 Electrical field connections, 250A Liebert STS2/PDU input with CB3 & CB3A
PSP11011
Rev. 1
FRONT
Doors and Accent Panels
Not Shown
CB5
A
B
C
A
B
C
A
B
C
.51" DIA.
(13mm)
Typ. 4 Places
See Ground
Busbar Detail B
CB3
CB3A
See Source
Busbar
Detail A
CB4
CB1
Source 1
Source 2
CB6
CB7
CB2
1. Phase, neutral and ground busbars are 1/4" thick.
2. Control wiring and power wiring must be run
in separate conduit. Output cables should be run
in a separate conduit from input cables.
3. Aluminum and copper clad aluminum cables
are not recommended.
4. All wiring is to be in accordance with national
and local electrical codes
Source 1 Busbar
Approx. 7.5 x 3.2
(191 x 81mm)
1/2"-13 PEM Nut
Typ. 4 Places
Source 2 Busbar
Approx. 7.5 x 3.2
(191 x 81mm)
1/2"-13 PEM Nut
Typ. 4 Places
SOURCE BUSBAR
DETAIL A
No Customer
Connections
No Customer
Connections
GROUND BUSBAR
DETAIL B
1.75" (44mm)
1.77"
(45mm)
8" (203mm)
3.5"
(89mm)
1.75"
(44mm)
Typical

Table of Contents

Other manuals for Vertiv Liebert STS2

Related product manuals