7. If you installed the AT-PWR150, AT-PWR250 or AT-PWR800 Power
Supply, install the power cord retaining clip on the AC plug. Press the
sides of the clip inward and insert the two ends into the holes on the
AC socket. Refer to Figure 38.
Figure 38. Installing the Power Cord Retaining Clip
Note
The AT-PWR250-80 and AT-PWR1200 Power Supplies do not
come with a retaining clip.
8. To install a second power supply, repeat this procedure, starting with
step 3.
9. If you installed only one power supply, perform the procedure in
“Installing a Blank Power Supply Slot Cover” on page 100.
10. Do one of the following:
To install an optional module, refer to Chapter 5, “Installing AT-
StackQS and AT-x9EM/XT4 Cards” on page 103.
To install the switch on a table, go to Chapter 6, “Installing the
Switch on a Table” on page 113.
To install the switch in an equipment rack, refer to Chapter 7,
“Installing the Switch in an Equipment Rack” on page 115.
To install the switch on a wall, refer to Chapter 8, “Installing the
Switch on a Wall” on page 121.