EasyManuals Logo

doble SFRA User Manual

doble SFRA
126 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #36 background imageLoading...
Page #36 background image
Sweep Frequency Response Analyzer (SFRA) User Guide
3-12 72A-2570-01 Rev. K 07/2011
7. When you are satisfied with the test results:
a. Disconnect the test lead clamps from each other.
b. Disconnect the reference ground clamps from each other.
8. Go to “Step 2: Ground the Transformer” on page 3-12.
Step 2: Ground the Transformer
Each time the SFRA test leads are connected, disconnected, or moved, apply
temporary static-discharge grounds to:
The bushings to which the SFRA test clamps will be applied
and
Any bushings to which jumpers will be applied
To ground a transformer for SFRA testing:
1. Open the switches to de-energize the transformer and disconnect it from
the rest of the substation (Figure 3.18).
Figure 3.18 De-energized and Disconnected Transformer
2. Ground all conductor or bus still connected to the transformer terminals
outside of the transformer bushings and windings (Figure 3.19).
Figure 3.19 Grounded Transformer

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the doble SFRA and is the answer not in the manual?

doble SFRA Specifications

General IconGeneral
Branddoble
ModelSFRA
CategoryMeasuring Instruments
LanguageEnglish

Related product manuals