3. Setting Up and Running a Test
72A-2570-01 Rev. K 07/2011 3-13
3. Remove the Isophase or GIS link (Figure 3.20).
Figure 3.20 Removed Isophase or GIS Link
4. Apply temporary static-discharge grounds (Figure 3.21).
Figure 3.21 Added Temporary Static-Discharge Grounds
5. Attach the SFRA test leads (Figure 3.22).