Chapter 5: Installation
112 EST3X Technical Reference Manual
3. Verify the field wiring. See Table 26 on page 128 “Field wiring tests.”
4. Install the PS10-4B Power Supply Board and any project-required
half-footprint modules.
5. Install any project required option cards on the back of the SFS1-CPU.
6. Install the SFS1-ELEC chassis assembly.
7. Install the optional 3X-PMI, if required for the project.
8. Power up the panel and download an optional initial startup database. See
“Initial power up” on page 43.
9. Install all project required option cards and control-display modules on the
chassis.
10. Connect field wiring.
11. Define the cabinet configuration, device loops, option cards, etc. for a final
3-SDU database, and then download it to the control panel. See
“Downloading a database” on page 67.
12. Install the 4X-CAB6D(R) door.
Component installation
The CAB6B backbox holds the power supply, electronics chassis assembly,
option cards, standby power supply batteries, and optional audio subsystem
components for the control panel. Figure 25 on page 113 shows the footprint
areas for each component. Refer to the installation sheet that came with the
component for installation instructions.