Revision 1 115 9/10/2019
5.18 Timers Tab
The Timers tab (Figure 5-40) offers another powerful way to trigger conditional gas run
requests other than the ones on the Streams tab. Manual Sequences can also be triggered
using start and stop timer set points.
Figure 5-40: Timers Tab
It is important to note that any conditional events will only commence after
the previous run is completed. For example: if a Zero gas run is scheduled
to start at 8:00 AM and just before that time a Sample run starts an
analysis, the Zero gas run will wait until the Sample analysis is finished.
Therefore all timed conditional events may not start at the exact time as
scheduled.