solution from corroding pipes, corrosion inhibitor should be mixed into the
glycol solution. For details about the mixing scheme, consult glycol experts.
Wrap thermal insulation layers for pipes connecting the water-cooled module.
A maximum of four water-cooled modules can be stacked, as shown in the
following gure.
Figure 4-18 Stacking scenario
(1) Water strainer
The water-cooled module should be installed on a concrete base. The base
requirements are as follows.
Figure 4-19 Concrete base dimensions (unit: mm)
(1) Mounting hole: 4 x M12
The following gure shows the operation area requirements for water-cooled
modules.
NetCol8000-A(045, 055, 060, 090, 120) In-room Air
Cooled Smart Cooling Product
User Manual 4 System Installation
Issue 05 (2020-10-10) Copyright © Huawei Technologies Co., Ltd. 62