5 Verifying the Installation
5.1 Indoor Unit Installation Verication
After the installation, check the items listed in Table 5-1, Table 5-2, and Table
5-3, and record the check results.
Table 5-1 Check items on the indoor unit
Check Item
Expected Result Actual Result
Cabinet The cabinet is installed properly, without
any tilts.
□ Passed □ Failed
The cabinet is secured to the bottom base
using bolts as required.
□ Passed □ Failed
The foreign matter inside the cabinet
such as cable ties and stubs is cleaned up.
□ Passed □ Failed
Fan The fan is secured. □ Passed □ Failed
The fan has no foreign matter inside. □ Passed □ Failed
The fan blades rotate properly. □ Passed □ Failed
Wet lm
humidier
The water inlet solenoid valve is secured
reliably and steadily.
□ Passed □ Failed
The wet lm is secured reliably and
steadily.
□ Passed □ Failed
Water inlet pipes are connected securely
without leaks.
□ Passed □ Failed
Compressor The sheet metal for transporting the
compressor is removed.
□ Passed □ Failed
The bolts on the compressor are
tightened.
□ Passed □ Failed
NetCol8000-A(045, 055, 060, 090, 120) In-room Air
Cooled Smart Cooling Product
User Manual 5 Verifying the Installation
Issue 05 (2020-10-10) Copyright © Huawei Technologies Co., Ltd. 150