Rigging work
12.8 Rigging work on the main boom
Operating Manual GMK6300L 3 112 xxx en 12 - 91
xx.xx.xxxx
Rigging for crane
operation
Slacken the hoist rope and derrick the main
boom simultaneously.
Raise the main boom until the boom head
is in a vertical position above the block
hook (1).
Detach the block hook from the retaining
ropes (2).
(A) – Pull the pin (3) out.
(B) – Raise the hook block (1) above the
hook (2 until the connecting points are
aligned.
Insert the pins (3) and secure them with the
retaining pins.