Installation
3-22
Part 1128350_02
E 2020 Nordson Corporation
Connecting Power Cables (contd)
WARNING! Risk of electrical shock. Steps 4 - 6 must be completed bef ore
using the melter.
4. Connect the ground lead (external protective grounding conductor) from
the power cable to the ground lug that is located on the chassis. The lug
is marked PE/G.
5. InsertthecorrectvoltageplugintoreceptacleX10onthepower
distribution PCA board. Ensure that the plug snaps into place.
If the plug contains a neutral lead, connect the neutral lead to receptacle
X9 and X11 on the power distribution PCA board.
6. Plug the electrical connector into receptacle TB1 on the power
distribution PCA board.
7. When the electrical service is completely installed a nd inspected in
accordance with local electrical codes and standards, close the E-Box
doorandreinstalltheE-Boxenclosuresidepanel.Switchonthelocal
power disconnect switch.