Maintenance belt conveyor
90 UM-PRORUNNER_Mk5-1.2-EN-US
9.2 Preventive maintenance schedule, belt carrier
9.2.1 Daily maintenance
/i
9.2.2 Weekly maintenance
/i
Item Task Action when required by the
check
Guards and covers Check for visible damage. Replace damaged guards and /
or covers.
Check if the mounting materials
are present and have been cor-
rectly placed.
Place the mounting materials or
correct the way in which they
have been fastened.
Entire machine Check for visible dirt. Clean the machine. Refer to
section 9.3.
Item Task Action when required by the
check
Conveyor belt Check for visible damage to the
surface and sides.
Replace the conveyor belt.
Refer to section 9.7.
Clean. Refer to section 9.3.
Driving drum Check for damage of the run-
ning surface and bearings.
Replace the driving drum. Refer
to section 9.7.
Clean. Refer to section 9.3.
Check for running sounds. Lubricate the bearings in the
driving drum. Refer to section
9.4.1.
Timing belt Check for damage. Replace the timing belt Refer to
section 9.7.
Check the alignment. Align the pulleys. Refer to sec-
tion 9.7.
Clean. Refer to section 9.3.
Pulley Check for dirt. Clean. Refer to section 9.3.
Check for visible deformation. Replace the pulley. Refer to
section 9.7.
Make sure the is running freely
and smoothly.
Replace the pulley. Refer to
section 9.7.
Check the alignment. Align the pulleys. Refer to sec-
tion 9.7.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Qimarox PRORUNNER Mk5 and is the answer not in the manual?

Qimarox PRORUNNER Mk5 Specifications

General IconGeneral
BrandQimarox
ModelPRORUNNER Mk5
CategoryAccessories
LanguageEnglish