Maintenance gravity roller conveyor
96 UM-PRORUNNER_Mk5-1.2-EN-US
10.2 Preventive maintenance schedule, gravity roller conveyor
10.2.1 Daily maintenance
/i
10.2.2 Weekly maintenance
/i
10.2.3 Monthly maintenance
/i
10.2.4 6-monthly maintenance
/i
Item Task Action when required by the
check
Guards and covers Check for visible damage. Replace damaged guards and /
or covers.
Check if the mounting materials
are present and have been cor-
rectly placed.
Place the mounting materials or
correct the way in which they
have been fastened.
Entire machine Check for visible dirt. Clean the machine. Refer to
section 10.3.
Item Task Action when required by the
check
Rollers Check for visible damage to the
surface and sides.
Replace damaged rollers. Refer
to section 10.5.
Clean. Refer to section 10.3.
Check for running sounds. Replace the roller. Refer to sec-
tion 10.5.
Make sure the rollers run freely
and smoothly.
Replace the roller. Refer to sec-
tion 10.5.
Item Task Action when required by the
check
Photocells and reflectors Check for visible damage. Replace the photocell and the
reflector if necessary. Refer to
section 10.5.
Check for loose parts. Fasten loose parts.
Clean. Refer to section 10.3.
Cabling Make sure that all cables are
securely fastened.
Connect the cables again if
necessary.
Item Task Action when required by the
check
All bolt connections Check all bolt connections. Tighten bolts using the correct
tool and torque.