6.6.3.5 Backing up the LAD/FBD program
Procedure
In order to back up an LAD/FBD program, proceed as follows:
1. Click in the toolbar on the Save project or Save project and compile changes button.
Alternatively, you can click the Accept and compile command in the LAD/FBD toolbar.
This command compiles the currently selected program as well as all other programs of
the same source.
However, the command does not save the changes.
You thus have the option of accepting changes to a program into the project without having
to save or compile the entire project again.
Additional references
For further information, refer to the Online Help and SIMOTION LAD/FBD Programming and
Operating Manual.
The Getting Started section of the SIMOTION SCOUT online help contains a detailed
description of a sample programming in SIMOTION SCOUT.
6.6.4 Using ST
6.6.4.1 Overview
Program creation steps
The creation of an ST program encompasses the following steps:
1. Create an ST source.
2. Save and compile the ST program.
3. Execute the ST program.
Configuring/parameterizing
6.6 Programming the SIMOTION application
SIMOTION SCOUT
Configuration Manual, 11/2016 125

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens SIMOTION SCOUT and is the answer not in the manual?

Siemens SIMOTION SCOUT Specifications

General IconGeneral
BrandSiemens
ModelSIMOTION SCOUT
CategoryControl Unit
LanguageEnglish

Related product manuals