Mounting and Commissioning
This chapter is intended for experienced commissioning staff. He must be familiar with the commissioning of
protection and control systems, the management of power systems and the safety rules and regulations.
Hardware adjustments to the power system data might be necessary. The primary tests require the protected
object (line, transformer, etc.) to carry load.
3.1 Mounting and Connections 312
3.2 Checking Connections 328
3.3 Commissioning 332
3.4 Final Preparation of the Device 352
3
SIPROTEC 4, 7SJ80, Manual 311
E50417-G1140-C343-A8, Edition 12.2017

Table of Contents

Other manuals for Siemens SIPROTEC 7SJ80

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens SIPROTEC 7SJ80 and is the answer not in the manual?

Siemens SIPROTEC 7SJ80 Specifications

General IconGeneral
Rated Frequency50/60 Hz
Rated Current1 A / 5 A
Operating Temperature-25°C to +55°C
Storage Temperature-40°C to +70°C
Current Transformer Inputs4
ApplicationProtection of feeders, motors, transformers, and generators
Rated Voltage100-240 V AC/DC
Communication ProtocolsIEC 61850, Modbus, DNP3, IEC 60870-5-103
DisplayGraphical LCD
MountingFlush mounting
Protection FunctionsOvercurrent, Earth fault
Communication InterfacesEthernet, RS485
HousingPlastic
WeightApprox. 1.5 kg