Vaisala RVP900 - Ascope Test; Table 99 Transmitter Phase Control Setup Checklist

Vaisala RVP900
484 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Test Equipment
KVM connected
Test Procedure
1. Enter the TTY setups through dspx.
2. Issue the Mz command.
Checklist
Table 99 Transmitter Phase Control Setup Checklist
Task Checked OK/Not OK Remarks
Test procedure completed successfully.
Parameters are set.
See 5.2.7 Mz — Transmissions and Modulations (page 126).
Test Passed
For Customer Date:
For Vaisala Date:
A.15 Ascope Test
Test Goal
Verify that the Ascope utility functions properly.
Background
The Ascope utility provides independent radar control and plotting for testing the radar and
RVP900.
Test Equipment
KVM connected
Test Procedure
1. Enter the TTY setups through dspx.
2. Issue the ascope command.
3. Verify that the Ascope utility launches and that the data display begins updating.
4.
Configure a DEFAULT startup and save it.
5. Exit and restart Ascope.
6. Verify that the default startup is properly restored.
Appendix A – Installation and Test Procedures
353