Checklist
Table 100 Ascope Setup Checklist
Task Checked OK/Not OK Remarks
Test procedure completed successfully.
Parameters are set.
See TTY nonvolatile setups in IRIS and RDA Utilities Guide.
Test Passed
For Customer Date:
For Vaisala Date:
A.16 Burst Pulse Alignment
Test Goal
Verify that the burst pulse is present and that its amplitude is sucient. This test also aligns
the burst pulse in the burst pulse sample window.
Test Equipment
KVM connected
Test Procedure
1. Use Ascope to select the desired pulse width at a saved PRF.
2. Enter the TTY setups through dspx.
3. Issue the Mb and turn
o burst pulse tracking.
4. Set the transmitter to radiate.
5. Issue the Pb and turn
o burst pulse tracking.
Use the L/R commands to find the burst pulse.
Use the l/r commands to
fine tune the position of the burst pulse in the burst pulse
window.
6. Adjust the width of the burst pulse window using the I/i command to be slightly
larger than the burst pulse (for example, ~50%).
7. Verify that the burst pulse power is in the range +1 ... -12 dBm per the tabular display on
the setup terminal.
RVP900 User Guide M211322EN-J
354