Maintenance
2124−2/A1
Winterthur Gas & Diesel Ltd.
1/ 8
Removal and Installation
Tools:
3 Manual ratchets 94016−004 2 Flange couplings 94201C
3 Shackles 94018D 1 Shackle 94201D
1 Lifting device 94201 1 Chain 94202L
consisting of: 1 Dismantling tool 94208
1 Lifting tool 94201A 1 Assembly tool 94345E
2 Holders 94201B
1. Preparation 1.......................................................
2. Cylinder Liner − Removal 2..........................................
2.1 Lifting Tool − Install 3.........................................
2.2 Cylinder Liner − Safe Storage 4................................
2.3 Lifting Tool − Removal 4.......................................
3. Water Guide Jacket − Removal 5.....................................
4. Water Guide Jacket − Installation 6..................................
5. Insulation Bandage − Removal 7.....................................
6. Insulation Bandage − Installation 7..................................
7. Cylinder Liner − Installation 8.......................................
8. Completion 8.......................................................
1. Preparation
1) Read the data in 0012−1 General Guidelines for Lifting Tools.
2) Drain the cylinder cooling water from the related cylinder.
3) Remove the cylinder cover (1, Fig. 1) together with the water guide jacket (2),
refer to 2708−1.
4) Remove the piston together with the piston rod gland, refer to 3403−1 and
2303−1.
5) Remove all lubricating quills and their pipes, refer to 2138−1.
6) Remove the gas admission valve, refer to 2140−1.
2016
Cylinder Liner