Loading...
Power On the Server
Log in to the Oracle ILOM web interface, click Host Management → Power Control and
select Power On from the Select Action list.
Log in to the Oracle ILOM command-line interface (CLI), and type the following command
at the Oracle ILOM prompt:
-> start /System
When the server is powered on and the power-on self-test (POST) code checkpoint tests
have completed, the green Power/OK status indicator (LED) on the front panel of the server
lights and remains lit.
Related Information
“Powering Down the Server” on page 51
“Reconnect Power and Data Cables” on page 167
168 Oracle Exadata Storage Server X5-2 High Capacity Service Manual • January 2018