Hold the TIMER soft-key for 3 seconds to turn the
timer off.
The timer can only be turned off under special MANU test
mode, however there is a limitation:
The timer cannot be turned off (limited to 240s) if the test
current is between 30mA and 40mA (IIT-2000/2010) or 80mA
and 100mA (IIT-5010/5000) in ACW mode.
The discharge time and initial test time cannot be edited.
Setting the Ramp Up Time
The Ramp Up time is the total time taken for the tester to
reach the test voltage level. The Ramp Up time starts after the
initial time (approximately 150ms) with a start voltage of 50
volts. The Ramp Up time can be set from 000.1 to 999.9
seconds. The Ramp Up time is only applicable for ACW, DCW
and IR tests.
Discharge time
Test V
time
Start V
Initial time
TEST TIMERAMP