Chapter 9 Operating instructions
S300
100 © SICK AG • Industrial Safety Systems • Germany • All rights reserved 8010948/YY96/2016-02-17
Subject to change without notice
Commissioning
9.2 Test notes
9.2.1 Pre-commissioning tests
Check the protective device as described below and in accordance with the applicable
standards and regulations.
Ensure that you do not place anybody at risk during initial commissioning of the
m
achine!
A
lways expect that the machine, system or the protective device does not yet behave as
you have planned.
Ensure that there are no persons in the hazardous area during initial commissioning.
Check the effectiveness of the protective device mounted to the machine, using all
selectable operating modes as specified in the checklist in the annex (see section 14.2
“Checklist for the manufacturer” on page 140).
Ensure that the operating personnel of the machine protected by the safety laser scanner
are correctly instructed by qualified safety personnel before being allowed to operate the
machine. Instructing the operating personnel is the responsibility of the machine owner.
Ensure that the information label Important information, which is included with the
safety laser scanner on delivery, is affixed to the machine in a place where it is clearly
visible for the operators. Ensure that the operators have the possibility to perform this
daily check correctly.
The annex to this document includes a checklist for review by the manufacturer and
OEM. Use this checklist as a reference before commissioning the system for the first
time (see section 14.2 “Checklist for the manufacturer” on page 140).
Document the adjustment of the safety laser scanner and the results of the testing
during initial commissioning in a traceable manner. For this purpose also print out the
complete configuration of the safety laser scanner (including protective field shapes)
and include these with the documentation.
Use the Create development dump... function in the CDS (right click on the COM inter-
face to which the safety laser scanner is connected). You can keep these data as a
backup and in this way document the state during initial commissioning at any time.
Your SICK representative will be pleased to provide you with advice on initial commis-
sioning.
9.2.2 Regular inspection of the protective device by qualified safety personnel
Check the system following the inspection intervals specified in the national rules and
regulations. This procedure ensures that any changes on the machine or manipulations
of the protective device after the initial commissioning are detected.
If major changes have been made to the machine or the protective device, or if the
safety laser scanner has been modified or repaired, check the system again as per the
checklist in the annex (see section 14.2 “Checklist for the manufacturer” on page 140).
WARNING
Recommendation
Note

Table of Contents

Other manuals for SICK S300

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the SICK S300 and is the answer not in the manual?

SICK S300 Specifications

General IconGeneral
Protection ClassIP65
Resolution30 mm
InterfaceRS-422, Ethernet
Power Supply24 V DC
Operating Temperature0 °C ... +50 °C

Related product manuals