Checking the consistency of the PH
We recommend that you check the consistency of the plant hierarchy each time you have
edited it. For this right-click on the multiproject and select the "Plant Hierarchy > Check
Consistency" command in the context menu.
The screenshot below illustrates a naming conflict relating to CFC charts which are in different
AS programs, but the same multiproject.
Creating and managing a PCS 7 project
5.6 Creating the plant hierarchy
Compendium Part A - Configuration Guidelines (V8.2)
78 Configuration Manual, 08/2016, A5E38166869-AA