OPERATION & MAINTENANCE MANUAL SWE50E/SWE60E/SWE70E/SWE80E9/SWE100
3.10.16 Lifting operation
Sling/chain should tightly bind the load
down, the workman should glove when
bind sling/chain.
Connect sling/chain with bucket lifting
ring, curled bucket, and retracted arm.
Before start, it should uniform the hand
signal with signalman.
Acquaint with the positions of all
workmen in the range of working area.
Connect hand rigging on the load and
ensure the people pulling hand rigging
away from load.
Try to lift the load before normal
operation.
Warning
It must follow all safety regulations when the
machine lifts objects.
Don’t use damaged chain, wire rope, or cord in
lifting work, or GBH may occur.
Don’t move the load suddenly.
Don’t move load on the top of human beings.
Don’t permit everybody adjacent to the load.
Ensure everybody away from lifted or
tightwire-tied and on the ground load, until the
chocks support the load or the load has been
stably placed on the ground.
Fix superstructure, and make the traveling
motor on the rear.
Don’t connect sling/chain on the bucket teeth.