Maintenance1132−2/A1
Winterthur Gas & Diesel Ltd.
6/ 15
3. Main Bearing Cover
No.1 − Removal
1) Remove the cover (1, Fig. 8) and the
holder (2).
2) Remove the round nuts (2, Fig.9) ,refer
to 1132−1.
3) Remove the oil pipe (1) from the main
bearing cover.
4) Do a check of the bearing clearance,
refer to 0330−1.
5) Do step 9) to step 21) above to install
the thrust device.
6) Attach the lug 94116C (Fig. 10) to the
main bearing cover (1).
7) Attach the shackle 94019G to the
platform.
8) Attach the spur-geared chain block
(H2) to the shackle 94019G and the lug
94116C.
9) Use the spur-geared chain block (H2)
to lift the main bearing cover (1).
2015
Main Bearing − Removal and Installation
Fig. 8
2
1
WCH03014
Fig. 9
Fig. 10
94019G
H2
94019K
1
WCH03014
WCH03021
1
2