Maintenance
11322/A1
Winterthur Gas & Diesel Ltd.
7/ 15
10) Attach the shackle 94019K (Fig. 11) to
the lug 94116C.
11) Attach the hook of the machine room
crane to the shackle 94109K. Apply a
light tension to the chain of the
machine room crane.
12) Disconnect the spur-geared chain block
(H2) from the lug 94116C.
13) Use the machine room crane to move
the main bearing cover (1) on to a
wooden underlay.
14) Remove the hook of the machine room
crane from the shackle 94019K.
2015
Main Bearing Removal and Installation
Fig. 11
94019K
94116C
94017028
94019K
1
WCH03014
H2