Maintenance33035/A2
Winterthur Gas & Diesel Ltd.
2/ 8
2. Removal
1) Use the pre-tensioning jack 94315 to
loosen the four round nuts (3, Fig. 2)
refer to 94034.
2) Remove the four round nuts (3) from
the elastic bolts (2).
3) Attach the two eye bolts (94045-M36)
to the bearing cover (1).
4) Attach the chain (94325) to the two eye
bolts (94045-M36).
5) Install the support (94116D) as follows:
a) Attach the shackle (94019P,
Fig. 3) to the top of the column.
b) Attach the sling (94039002) to
the support (94116D).
c) Attach the chain block (H3) to the
sling (94039002) and the shackle
(94019P).
d) Attach the sling (94039015) to
the gallery as shown.
e) Attach the shackle (94019H) to
the support (94116D).
f) Attach the chain block (H5) to the
sling (94038015) and the shackle
(94019H).
g) Operate the chain blocks (H3, H5)
to lift the support (94116D) to the
position shown.
h) Attach the support (94116D) to the
column with the pin (1).
i) Remove the sling (94039002).
j) Remove the chain block (H3) from
the sling (94039002).
Note: Keep the tension on the sling
(94039015) and the chain
block (H5).
2017
Top End Bearing Cover Removal, Inspection and Installation
Fig. 2
WCH02662
94325
94045M36
2
1
3
Fig. 3
94039015
H5
WCH03784
H3
H3
94039002
1
94116D
94019H
94116D
94019P