Maintenance
33035/A2
Winterthur Gas & Diesel Ltd.
1/ 8
Top End Bearing Cover Removal, Inspection and
Installation
Tools:
1 Spur-geared trolley 94015008 1 Lifting support 94116D
2 Manual ratchet, 2500 kg (H1, H2) 94016012 1 Platform 94143
2 Spur-geared chain block, 2500 kg (H3, H4) 94017029 1 Pre-tensioner 94315
1 Spur-geared chain block, 7500 kg (H5) 94017045 1 Sling, 2000 kg 94039002
2 Shackle, 13500kg 94019P 1 Chain 94325
1 Sling, 2000 kg 94039015 2 Eye bolts, M36 9404536
2 Shackle, 8500kg 94019L 1 Shackle, 3250 kg 94019H
2 Shackle, 2000kg 94019G
1. Preparation
Note: On some engine types, the supply unit is in a different position. It can be
necessary to remove some platform components to get access to the top
end bearing cover.
Note: This procedure is for engines where the supply unit is near the middle of
the fuel side on engines with 9 to 12 cylinders. For engines with 6 to 8
cylinders, the procedure can look different because the supply unit is in a
different position on the engine.
1) Read the data in 00121 General Guidelines for Lifting Tools.
2) If necessary, remove the applicable platform components to get access to the top
end bearing cover.
3) Prepare the piston, refer to 33033, paragraph 1.
4) Install the platform (94143, Fig. 1).
5) Make sure that the turning gear is locked to prevent movement of the crankshaft.
Fig. 1
WCH03784
94143
2017
Connecting Rod