GreenDrill control terminal 3.2
56
GreenDrill BAH0054-9 11.17
6.7 Starting work at the beginning of the field
Do not switch off the blower fan during use.
Before starting work
1. Close the seed hopper cover.
2. Check if the deflector plates have the same distance.
3. Check that the seed delivery hoses drop downwards along the entire length.
Work commencement
1. Instruct any people in the area to stand at a minimum distance of 10 m from the implement.
2. Start the tractor.
3. Press the
button.
The green control lamp above the button is illuminated.
The control terminal is switched on
The two-part display shows
the implement version
and then the seeding shaft speed [speed in %].
4. Press the
button.
The red control lamp above the button is flashing
The blower fan begins to rotate
When the blower fan nominal speed is reached, the control lamp stops flashing and is con-
stantly illuminated.
5. Press the
button.
The green control lamp above the button is illuminated.
The seeding shaft rotates at the nominal speed.
The seed is metered.
To prevent blockage in the seed tube lines, the seeding shaft can only
be switched on when the blower fan is running.
The speeds of the seeding shaft and blower fan do not change with
changing working speeds.