GreenDrill control terminal 5.2
GreenDrill BAH0054-9 11.17
71
10. Select the display with the
buttons.
11. Confirm the selection with the
button.
The calibration starts.
The seeding shaft begins to rotate (without blower fan).
The seeding shaft stops automatically after the set time
has elapsed.
During calibration, keep the calibration button (if availa-
ble) pressed. The seeding shaft stops after the button is
released.
Do not select a shorter duration for the calibration than
specified (see point 8).
12. Weigh the collected seed.
13. Select the display with the
buttons.
14. Confirm the selection with the
button.
15. Enter the weight [kg] of the collected seed on the control termi-
nal using the
buttons (e.g. 3.25 kg).
16. Confirm the entry with the
button.
The required seeding shaft speed is calculated automati-
cally.
The theoretical seeding shaft speed is calculated from the ini-
tial data (working width and forward speed). If the calibrated
seeding shaft speed deviates by more than 3%
the adjacent display appears.
repeat the calibration.
Display after correctly terminated calibration test.
If no button is pressed, the display switches to the main menu
after approx. 5 seconds (see page 66).