80-0000010B OM
276
Table 6.1.1 – Types of scheduled technical maintenance
Types of technical maintenance Intervals, h
Technical maintenance during operating run-in
1)
TM before, during and after run-in
(after 30 hours of operation)
Shift-time (STM) 8-10
First technical maintenance (TM-1) 125
Additional technical maintenance (2TM-1) 250
Second technical maintenance (TM-2) 500
Third technical maintenance (TM-3) 1000
Special technical maintenance 2000
General technical maintenance As and when necessary
Seasonal technical maintenance (TM-SS и TM-
AW)
While transfer to autumn-and-
winter operation (TM-AW) and to
spring-and-summer (TM-SS)
Technical maintenance not coinciding with the
set intervals of TM-1, 2TM-1, TM-2, TM-3 and
special TM
–
Technical maintenance in special operating
conditions
During preparation of the tractor
operation in special conditions
Technical maintenance during storage
2)
In case of long-term storage
___________________________________________________________________________________________________________________________________________________________
1)
Data on the technical maintenance, carried out by the operator before, during and
after the tractor run-in are given in subsection 4.4 “Tractor final assembly and run-in”.
2)
Data on technical maintenance performed by the operator on long storage of the
tractor are shown in section 8 “Tractor storage” of this Manual.
Deviation of + 10% for TM-1, 2TM-1 and TM-2 and 5% for TM -3 from the set inter-
vals of TM are permitted (advancing or delayed TM) depending on the operating condi-
tions of the tractor.