15 Suction conveyor, lance + fabric tank
15.2 Installation, removal pot with lance
1.) Flange ring
Dismount the flange ring from the removal pot.
Fit the flange ring over the sown-on “collar” of the fabric tank.
Flange ring
2.) Removal pot
Insert the screws through the flange ring from ABOVE!
This prevents damage to the tank fabric.
Bolt the flange ring, collar, and extractor pot together.
Removal pot
3.) Earth connection for the hoses
To ensure that static discharges do not occur when transporting the
bulk material, the entire transport hose and fuel extractor system
must be connected in a manner that is electrically conductive and
it must they grounded via the equipotential busbar!
Strip the earth strand 5 cm.
Bend the earthing strand into the hose.
Earthing wire
1
4.) Connecting the hoses
Slide 2 hose clamps over the nozzles.
Slide the hose clamp completely over the inside connector.
Connect the return flow hose 1 on the upper connecting piece.
(Hose from the turbine)
Connect the pellet hose 2 on the upper connecting piece.
(Hose to the suction tank cover)
Tighten the hose clamps – the connection must be sealed and secured
so that it cannot be pulled off.
Connect hoses
15.3 Lay out transport hose see point 13.3
15.4 Fabric tank see section 9
15.5 Final inspection
Ensure that ALL components and connections are correctly installed!
To conclude, ensure that the conveyor system is free of foreign objects!
MA-Easyfire 10.2008_EN.indd 134MA-Easyfire 10.2008_EN.indd 134 30.03.2009 13:31:29 Uhr30.03.2009 13:31:29 Uhr