2NC/2NF/2NG/2NN/3P7/3P8/3P9
1-5-37
5. Release the developer electric wire
from the hook of the electric wire and
then remove the electric wire cover by
releasing the lock lever.
6. Remove the developer electric wire
connector.
Figure 1-5-63
7. Pull the developer evacuation lever for-
ward.
8. Remove the developer unit by pulling
forward.
9. Check or replace the developer unit and
refit all the removed parts.
10. When replacing the new unit,proceed
as follows:
1)Performs maintenance mode U130
(Set Toner Install) (see page 1-3-49).
2)Performs maintenance mode U157
(Dev Time) (see page 1-3-54).
3)Performs maintenance mode U158
(Dev Cnt) (see page 1-3-54).
Figure 1-5-64
Lock lever
Electric wire cover
Developer
electric wire connector
Hook
Developer
evacuation lever
Developer unit