Commissioning
38 MCS100E Operating Instructions 8009504/VYWA7/V3-1/2018-01 © SICK AG
Subject to change without notice
4.1 Commissioning
As soon as connected to line power (power plug connected), MCS100E automatically starts
operation.
In particular, check before power-on:
– Power voltage adjustment (
→
p. 35, §3.8.1).
– Fuse ratings (depend on voltage) (
→
p. 36, §3.8.1.2).
– Correct connection of the sample gas lines (
→
p. 24, §3.2.2.1).
– Correct connection of the fiber optical cables (
→
p. 26, §3.2.3.1).
For connection to line power, a grounded cord connector is used (the MCS100E does
not have a power switch).
Figure 16 Power connection at the bottom of MCS100E
The MCS100E is supplied with all parameters set.
It will start operating immediately after power-on.
NOTICE:
If a cold instrument is installed in a warm environment, there is a risk of
condensation inside the instrument.
Allow the instrument to stand for approx. 24 h to adopt ambient
temperature before switching on the supply voltage.
NOTICE:
The heating-up time of MCS100E is approx. 4 h.
Do not apply condensing gas to the instrument before the end of the
heating-up time.