24. Functional Testing &
Preventative Maintenance
Schedule
24.1 Functional testing
Every three months the user shall perform the
functional test as described on page 160.
24.2 Preventative Maintenance
24.2.1 Preventative Maintenance Model M-1
Part Numbers:
12 months
Uses 12 month kit ................ P/Nº: N9010/12/M
24 months
Uses 24 month kit ................ P/Nº: N9010/24/M
PPM kit A
Uses the following................ P/Nº: N9010/00A/0M1
PPM kit B
Uses the following................ P/Nº: N9010/00B/0M1
24.2.2 Preventative Maintenance Model N
12 month
Uses 12 month kit ................P/Nº: N9010/12/M
24 months
Uses 24 month kit ................P/Nº: N9010/24/M
PPM kit C
Uses the following................ P/Nº: N9410/00C/0N1
A service manual is available for use by
qualified engineers who have been trained by
SLE on this product. Contact SLE or your
distributor for further information.
Warning: Preventative Maintenance, Overhaul
and Calibration of this ventilator should only
be carried out by a SLE trained hospital
engineer or an SLE service engineer.
Note: If the ventilator is in use on a patient,
the user can postpone the functional testing
to a time when the ventilator is not in use.
Year Use 12
month
PPM kit
Use 24
month
PPM kit
Use PPM
kit A
Use PPM
kit B
1
2
3
4
5
6
7
8
Year Use 12 month
kit
Use 24 month
kit
Use PPM
kit C
1
2
3
4
5
6
7
8

Table of Contents

Related product manuals