8.4 Zero Point Return (ZRET)
8-29
8
(3) Operating Procedure
(4) Holding
Holding execution is not possible during zero point return operation. The Command Pause bit (OB

090) is
ignored.
(5) Aborting
Axis travel can be stopped during command execution and the remaining travel cancelled by aborting execution
of a command. A command is aborted by setting the Command Abort bit (OB

091) to 1.
Set the Command Abort bit (OB

091) to 1. The axis will decelerate to a stop. When the axis has stopped, the
Positioning Completed bit (IB

01C) will turn ON.
This type of operation will also be performed if the motion command is changed during axis movement.
No. Execution Conditions Confirmation Method
1 There are no alarms. Both IL

02 and IL

04 are 0.
2 The Servo ON condition. IB

001 is ON.
3 Motion command execution has been completed. IW

08 is 0 and IB

090 is OFF.
Set the motion setting parameters.
The parameters that need to be set will
depend on the zero point return method.
Refer to the previous pages for details.
• The software limit function will be enabled after the Zero Point
Return operation has been completed.
• The Command Pause (OB

090) cannot be used.
• Set OB

091 to 1 to abort the command.
Execute the zero point return (ZRET)
motion
command.
• Set OW

08 to 3.
Zero point return operation starts.
• IW
08
will be 3 during execution.
Zero point return operation completed.
• IB

0C5 will turn ON.
Execute NOP motion command.
• Set OW

08 to 0.

Table of Contents