Quick installation and commissioning flowchart
SeeTask
Type designation key (page 50)
Identify the frame of your drive: R1…R9.
Guidelines for planning the electrical installa-
tion (page 87)
Plan the installation: select the cables, etc.
Examine the ambient conditions, ratings and
required cooling air flow.
Technical data (page 231)
Mechanical installation (page 53)
Unpack and examine the drive.
Make sure that all necessary optional modules
and equipment are present and correct.
IEC: Grounding system compatibility
check (page 115)
If the drive will be connected to another system
than symmetrically grounded TN-S system: Ex-
amine if you must disconnect the EMC filter or
ground-to-phase varistor.
North America: Grounding system compatibility
check (page 166)
Mechanical installation (page 53)
Install the drive on a wall.
Routing the cables (page 103)
Route the cables.
IEC: Measuring the insulation (page 114)
Measure the insulation of the input cable and
the motor and the motor cable.
North America: Measuring the insula-
tion (page 164)
IEC: Connecting the power cables (page 122)
Connect the power cables.
North America: Connecting the power
cables (page 172)
IEC: Connecting the control cables (page 140)
Connect the control cables.
North America: Connecting the control
cables (page 187)