b) Set Specify Time Between Recurring Runs to 0 days, 0 hours, and 0 minutes.
Set up SMV automatic execution using ProLink III
Procedure
1. Select one of the following paths to access the SMV scheduler .
• Choose Device Tools > Diagnostics > Meter Verification > Meter Verification Scheduler.
• Choose Smart Meter Verification Overview > Tools > Schedule Smart Meter Verification.
2. To schedule a single test:
a) Set Specify Time Until Next Run to the number of days, hours, and minutes to elapse before the
test is run.
b) Set Specify Time Between Recurring Runs to 0 days, 0 hours, and 0 minutes.
3. To schedule a recurring execution:
a) Set Specify Time Until Next Run to the number of days, hours, and minutes to elapse before the
first test is run.
b) Set Specify Time Between Recurring Runs to the number of days, hours, and minutes to elapse
between runs.
4. To disable scheduled execution:
a) Set Specify Time Until Next Run to 0 days, 0 hours, and 0 minutes.
b) Set Specify Time Between Recurring Runs to 0 days, 0 hours, and 0 minutes.
Set up SMV automatic execution using the Field Communicator
Procedure
1. Choose Service Tools > Maintenance > Routine Maintenance > SMV > Automatic Verification.
2. To schedule a single test:
a) Set Hours Until Next Run to the number of hours to elapse before the test is run.
b) Set Recurring Hours to 0.
3. To schedule a recurring execution:
a) Set Specify Time Until Next Run to the number of days, hours, and minutes to elapse before the
first test is run.
b) Set Specify Time Between Recurring Runs to the number of days, hours, and minutes to elapse
between runs.
4. To disable scheduled execution:
a) Set Specify Time Until Next Run to 0 days, 0 hours, and 0 minutes.
b) Set Specify Time Between Recurring Runs to 0 days, 0 hours, and 0 minutes.
Configuration and Use Manual Measurement support
MMI-20025166 March 2019
Configuration and Use Manual 205