8-44 Section 8-3 - Internal Component Replacement Procedures
7) Re-install the battery as described in the Battery Installation Procedure on page 8 - 6.
8) Return the bearing handle as described in the Bearing Handle Installation Procedure on page 8 - 4.
9.) Turn ON the system and boot-up.
10.)Perform the PMC Update procedure, as described in Installation of PMC Version on page 8 - 135.
11.)Perform the BIOS Update procedure, as described in BIOS Firmware Update on page 8 - 118.
Note: If both the Back End and the Hard Disk are being replaced simultaneously, continue to the
next step. If only the Back End is being replaced, skip step 12 and proceed to step 13, below.
12) Perform the steps required to burn the LCD type onto the newly-installed Back End, as described
in step 9 on page 8-56 through step 12 on page 8-57.
13) Perform a complete functional check of the system, as described in Chapter 4 - .
14.)Proceed to perform the following functionality tests:
- SafeLock Cart - Grounding Continuity on page 10 - 23 - only if the
Vivid i n/ Vivid q N system is currently mounted on the SafeLock cart
- SafeLock Cart - Chassis Current Leakage Test on page 10 - 25
- Calibration Tests on page 7 - 25
- Full System Test on page 7 - 10