GETTING STARTED
Manual Part Number
3. GETTING STRTED
3.1. System Power On
Refer to the relevant operator’s manual in case a Storage Cabinet is used to store the
Exablate Prostate cradle.
[N-5]
Ensure that all system components and accessories are present and intact, before starting
the treatment.
[W-46]
Start up the system in the following sequence:
1. Confirm that the MR console had been rebooted at the beginning of the day. If it had not - please
reboot it.
2. Undock the imaging table.
3. Connect the patient table to the MR scanner (see Figure 3-1):
◼ Dock the patient table to the MRI scanner.
◼ Lock the connector lever by pulling it toward the magnet bore.
◼ Do not un-dock the table when the connector lever is secured.
◼ Ensure that the patient table is connected to the MRI and the connector lever is
secured before turning on the main power switch. Do not disconnect the table
when the main power is on except in an emergency.
[W-12]