• If you install jumpers, obey the specifications for units manufactured
before 3/2023.
5.2.8.2. Units manufactured before 3/2023
NOTE
In double and triple cabinet units manufactured after 3/2023, the AC supply terminal
blocks of the cabinets are not jumpered together at the factory. If you install jumpers,
one cabinet's main switch does not shut off the power in the other cabinet(s) of the
unit. You must mark the units clearly to indicate the danger.
• You can remove the jumpers on site. In this case obey the specifications
for units manufactured after 3/2023.
•
When the AC supply terminal blocks of double cabinets are jumpered
together, connect one AC mains power cable to one of the cabinets.
• When the AC supply terminal blocks of triple cabinets are jumpered
together, connect one AC mains power cable to each of the end
cabinets. Do not connect an AC mains power cable to the middle
cabinet.
5.2.9. Installing the DC output power cables
NOTICE
Prevent the AC and DC power cables from crossing to minimize electro-magnetic
compatibility (EMC) disturbances.
NOTICE
Use ferrules for terminating fine-stranded wires (IEC 60228 class 5 and 6 or
equivalent).
NOTE
Label the cables clearly at both ends. Documenting which output supplies which
charging point helps with later troubleshooting.
NOTE
Tighten each screw terminal to the correct torque. The tightening torque is marked
on the terminal block.
NOTE
After you connect the cables to the screw terminals, make sure that the voltage
measurement wires are still correctly connected.
The DC output power cable can be shielded or non-shielded. Non-shielded
cables must have 5 wires (2 x DC+, 2 x DC-, PE).
Connect the PE wires in the Satellite to the installation flange using the PE
clamps. The PE clamps are included in the delivery, in a plastic bag.
CHARGING EQUIPMENT FOR ELECTRIC VEHICLES INSTALLATION MANUAL
CONFIDENTIAL – CERTIFIED PARTNERS 93 REV 2.40 EN 04-2024