7. FINISHING THE INSTALLATION
CAUTION
When you have connected all cables correctly, make sure that the fuse rating setting
is correct in the charging power unit.
NOTE
Make sure that the expansion tank in the liquid cooling unit is approximately 1/3 full
before you start operation. See 5.1.7: Moving and lifting Liquid Cooled Satellite.
NOTE
Upload all available site documentation to ChargEye to help with future
troubleshooting.
The electrical installation is done when:
•
A qualified electrician who has completed the Kempower
certification training has installed and connected all cables
and electrical components as specified in the electrical design
documentation.
• The main switch of the charging power unit has been correctly
configured.
• The control module and mains fuse settings obey the electrical design.
• The electrician has done all required electrical safety tests according to
local regulations, and stored the test reports on-site.
• The electrical installation contractor has done the required inspections
for all site units, and delivered the checklist to the commissioner of the
charging site:
•
7.1.1: Sensory inspection
• 7.1.2: Electrical installation and safety inspection
7.1. Inspecting the installation
CAUTION
Know and obey the local laws, regulations, and requirements.
CAUTION
Keep the AC main power supply disconnected during the inspection.
Do the installation inspection when the electrical installation is done. See 7:
Finishing the installation.
The commissioning checklist is a separate document provided
by Kempower. This is an overview of the items to be
CHARGING EQUIPMENT FOR ELECTRIC VEHICLES INSTALLATION MANUAL
CONFIDENTIAL – CERTIFIED PARTNERS 114 REV 2.40 EN 04-2024