Item to inspect
Power Units
Station Charger
Satellite
Satellite Version 2
Liquid Cooled Satellite
Control Unit
AC Satellite
AC Satellite
with charging cables
AC supply wires correctly labeled (L1–
L2–L3)
• •
AC supply phases correctly reordered
(multiple AC satellites)
• •
Ethernet cable connected to EXT port of
control board (option)
• •
8. COMMISSIONING
NOTICE
Commissioning done by an unapproved partner will void the warranty.
During commissioning the charging site is connected to the ChargEye
backend system and the charging site's set-up and functions are
configured. As a general rule, approximately one hour is needed to
configure a charging site with one charging power unit and four Satellites.
You do not have to be a licensed electrician to do the commissioning but
you must have extensive knowledge of electrical installations and have
completed the Kempower certification training. We recommend that you
have a licensed electrician on site during commissioning to repair possible
electrical installation errors.
Before you start the commissioning make sure that:
•
The installation has been inspected and approved.
• You have received the electrical safety test report.
• The site is online.
• If necessary, remote commissioning support has been booked in
advance from
Kempower Technical Support.
•
All necessary OCPP information is available (option).
CHARGING EQUIPMENT FOR ELECTRIC VEHICLES INSTALLATION MANUAL
CONFIDENTIAL – CERTIFIED PARTNERS 117 REV 2.40 EN 04-2024