12 Pellet Stirrer Plus
10.) Screw on the stirrer worm
Dismount the drilling template and conveyor worm, bolt the connecting
bolts and shaft joint together.
11.) Place the insulating boards underneath
2 pc. Insulating boards should be placed under each leg.
12.) Place insulating boards under the fuel extractor
2 pc. insulating boards should be properly shortened and placed
underneath
Attention!
Ensure that the gear unit shaft and the trough centre are horizontal
and at the same height.
13.) Bores for floor plugs
For the gear unit holder and for all adjustable feet, drill bores for the
floor plugs.
14.) Prepare floor plugs
To avoid acoustic transmission prepare the floor plugs with washer,
acoustic insulation washer and rubber hose.
MA-Easyfire 10.2008_EN.indd 122MA-Easyfire 10.2008_EN.indd 122 30.03.2009 13:31:09 Uhr30.03.2009 13:31:09 Uhr