7-18 Maintenance
D-H023.0906EN
innovators in agriculture
Measure the Feed Portion
The steps in this sub-section must be done for all installed feeding
valves.
1. Select [Feed type]
2. Select [Start dose].
3. Wait until the feed unit is finished.
4. Put a bucket on the scales.
5. Reset the scales to zero.
6. Remove the bucket.
7. Go into the box via the exit gate.
8. Put the feed from the feed bin in the bucket.
9. Go out of the box via the exit gate.
10. Put the bucket with the feed on the scales.
11. Make a note of the weight.
12. Empty the bucket.
Adjust the Feed Portion
The steps in this sub-section must be done for all installed feeding
valves.
1. Next to the field 'Feed portion' at the right and side: enter the
value you noted.
2. [Save portion sizes]
Close Up
1. Put the milking robot in operation with the X-Link (page 6-1).
2. Unblock the cow traffic.
7.7 Robot Arm Systems
7.7.1 Clean the Bleed Holes
Special Tools
Bleed hole needle (1, fig. 36,
page 7-19)
Preparation
1. Take the milking robot out of operation with the X-link (page 6-1).
2. Move the robot arm to the service position (page 6-11).
Clean
1. Clean the bleed hole (2) in each teat cup with the bleed hole
needle (1).

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the LELY ASTRONAUT A3 Next and is the answer not in the manual?

LELY ASTRONAUT A3 Next Specifications

General IconGeneral
BrandLELY
ModelASTRONAUT A3 Next
CategoryFarm Equipment
LanguageEnglish

Related product manuals